NEWS Apr 08, 2026

Fuel Tanks Welding in Progress for DWASAL Fuel Station 4-April

Welding of fuel storage tanks for the DWASAL fuel station is underway, marking progress in setting up fuel inf...

Read More →
NEWS Apr 08, 2026

DWASAL Vehicle Parking Fence Takes Shape 3-April

Plastering works at the DWASAL weighbridge office are in the final stage, bringing the building closer to comp...

Read More →
NEWS Apr 08, 2026

DWASAL Weighbridge Office Nears Completion with Plastering Works – 3 April

Plastering works at the DWASAL weighbridge office are in the final stage, bringing the building closer to comp...

Read More →
NEWS Apr 08, 2026

DWASAL Conducts Loaded Truck Testing on Weighbridge – 1 April

DWASAL begins weighbridge testing using loaded trucks to verify accuracy and performance before full operation...

Read More →
NEWS Apr 08, 2026

DWASAL Weighbridge Installation testing Begins with Massive Stone Placement – 1 April

Installation of the DWASAL weighbridge begins with offloading and positioning of massive foundation stones usi...

Read More →
NEWS Mar 31, 2026

Weighbridge System Improvements – 31st March

DWASAL carried out key improvements on its weighbridge system to enhance accuracy, performance, and operationa...

Read More →
NEWS Mar 31, 2026

Office and Weighbridge Area Improvements

DWASAL has enhanced its office and weighbridge environment to improve organization, workflow, and operational...

Read More →
Operational Environment Enhancement Snapshot
NEWS Mar 31, 2026

Operational Environment Enhancement Snapshot

A recent snapshot shows improvements in DWASAL’s operational environment, emphasizing better organization and...

Read More →
NEWS Mar 31, 2026

Weighbridge System Upgrade Activities – 30th March

DWASAL conducted upgrade activities on its weighbridge system to improve functionality and overall performance...

Read More →
NEWS Mar 26, 2026

Weightbridge Setup Progress (Video)

Work on installing the weightbridge is actively ongoing, bringing the project closer to completion.

Read More →
Weightbridge Installation Progress at DWASAL Site
NEWS Mar 26, 2026

Weightbridge Installation Progress at DWASAL Site

Installation of the weightbridge structure is progressing steadily, marking a key milestone in improving opera...

Read More →
NEWS Mar 23, 2026

DWASAL Project Progress: Office & Weighbridge Update – 20 March Type *

Construction advances at DWASAL as the office building reaches lintel level while the weighbridge is fully cem...

Read More →
DWASAL Office Building Reaches Lintel Stage – 20 March
NEWS Mar 23, 2026

DWASAL Office Building Reaches Lintel Stage – 20 March

The DWASAL office building has reached lintel level, marking a key milestone in structural development as wall...

Read More →
Weightbridge Foundation Works in Progress – 19 March Update
NEWS Mar 19, 2026

Weightbridge Foundation Works in Progress – 19 March Update

Foundation construction for the weightbridge is underway, marking an important early stage of the project.

Read More →
19 March Update: Weightbridge and Office Construction Progress
NEWS Mar 19, 2026

19 March Update: Weightbridge and Office Construction Progress

Concrete works for the weightbridge platform have been successfully completed, marking a key milestone in the...

Read More →
NEWS Mar 17, 2026

Foundation Construction Update (Video) – 17 March

Video showing real-time progress of foundation works at the site.

Read More →
Foundation Works Progress – 17 March
NEWS Mar 17, 2026

Foundation Works Progress – 17 March

Snapshot showing ongoing foundation works at the construction site.

Read More →
NEWS Mar 15, 2026

Construction Progress Video Update – 15 March

Video showing the ongoing construction progress of the office building and weightbridge facility.

Read More →
Construction Activities Continue at Project Site – 15 March Update
NEWS Mar 15, 2026

Construction Activities Continue at Project Site – 15 March Update

Update on the progress of ongoing construction works as of 15 March.

Read More →
NEWS Mar 13, 2026

Weightbridge Office Construction Progress Update

Construction of the weightbridge office is progressing as masonry works and wall structures continue at the pr...

Read More →
Weightbridge Foundation Reinforcement Works in Progress
NEWS Mar 13, 2026

Weightbridge Foundation Reinforcement Works in Progress

DWASAL construction team continues reinforcement works for the weightbridge foundation, preparing the structur...

Read More →
NEWS Mar 11, 2026

DWASAL BEINBEN Trucks Arrive at Tanga Port

New DWASAL BEINBEN trucks for transporting materials to customers have arrived at the Port of Tanga, marking a...

Read More →
Weight Bridge Concrete Foundation Taking Shape
NEWS Mar 10, 2026

Weight Bridge Concrete Foundation Taking Shape

A wide view of the DWASAL construction site shows the completed concrete foundation for the upcoming weight br...

Read More →
A Stunning View of the DWASAL Construction Site
NEWS Mar 10, 2026

A Stunning View of the DWASAL Construction Site

A beautiful view of the DWASAL project site shows ongoing activities and the progress of infrastructure develo...

Read More →
Grader Continues Site Leveling Work at DWASAL
NEWS Mar 10, 2026

Grader Continues Site Leveling Work at DWASAL

The grader continues with leveling and preparation work at the DWASAL site to ensure the ground is properly pr...

Read More →
NEWS Mar 10, 2026

Staff Toilet Facilities Completed at DWASAL Site

The construction and installation of staff toilet facilities at the DWASAL site has been successfully complete...

Read More →
Weighbridge Foundation Completed at DWASAL
NEWS Mar 10, 2026

Weighbridge Foundation Completed at DWASAL

The foundation of the weighbridge at Dodoma Washed Sand Limited has been successfully completed and the projec...

Read More →
NEWS Mar 10, 2026

Night Shift Construction in Progress at DWASAL

Construction work at the DWASAL site continues during the night shift as engineers and workers remain committe...

Read More →
NEWS Mar 10, 2026

Weighbridge Construction Activities Continue at DWASAL

Construction activities for the weighbridge area are progressing at Dodoma Washed Sand Limited, with engineers...

Read More →
Ujenzi wa Sehemu ya Mizani Umeanza DWASAL
NEWS Mar 10, 2026

Ujenzi wa Sehemu ya Mizani Umeanza DWASAL

Dodoma Washed Sand Limited imeanza rasmi ujenzi wa sehemu ya mizani katika eneo la mradi. Wahandisi pamoja na...

Read More →